Road Construction Updates

Get road construction updates.
Subscribe now for email updates on the city's major road construction projects.

The City of Irving works hard to minimize the disruption caused by road construction, and in doing so, wants to keep everyone apprised of construction projects, timelines and traffic flow. While we apologize for the traffic cones, we also know construction means new and improved infrastructure, as well as community growth. Growth brings in the tax revenue needed to continue offering quality services and maintain Irving resident taxes and fees that are among the lowest in North Texas.

Committed to keeping the community informed on capital improvement projects, residents can receive email updates on road construction projects affecting traffic by subscribing to the city’s listserv. Subscribe now for free email updates.

City of Irving Projects

  • O’Connor BoulevardState Highway 114 to Riverside Drive
    Status: Traffic on Las Colinas Boulevard is reduced to one lane in each direction at the intersection of Las Colinas Boulevard and O’Connor Boulevard to facilitate the installation of two water mains, a storm sewer system and pavement. The Las Colinas Boulevard lane closures will remain in effect through approximately November 2014. MORE

  • Manhole Rehabilitation Project (maps)
    Irving has 120 wastewater manholes throughout the city in need of repair and/or replacement. During repairs, each location will typically have a single lane of traffic affected for approximately three days. The project has an estimated completion date of May 2015.

  • Cheyenne Street – at Northwest Park Recreation Center (maps)
    Status: Expect heavy construction traffic in the recreation center parking lot and along Cheyenne Road. Work will begin on demolishing and reconstructing the tennis courts. Portions of the Northwest Recreation Center parking lot will be closed and used for staging. The courts are scheduled to be back in service around Sept. 15.

  • Grauwyler Road - from southbound frontage road of Loop 12 to Darr Street (map)
    * Status: The eastbound lanes of Grauwyler Road between Tucasa Drive and Darr Street will be closed Sept. 2 through 12 for gas main replacement work by Atmos Energy. The gas main will also be replaced at the crossing of Grauwyler Road and Tucasa Drive Sept. 13 through 14. Work will occur between 7 a.m. and 7 p.m., Monday through Saturday, and 7 a.m. to 5 p.m. on Sunday.
    View the weekday detour map | View the weekend detour map

    After the gas main is replaced, Grauwyler between Tucasa Drive and Darr Street will be repaved. The entire Grauwyler Road paving project is anticipated to be completed by early October.

  • Irving Boulevard - at Wildwood Drive
    * Status: Atmos Energy crews and contractors will oversee a natural gas flaring at Irving Boulevard and Wildwood Drive starting at 10 a.m. Aug. 29. Flaring is a standard industry practice to safely burn natural gas that must be removed from a pipeline. Atmos must flare in order to replace segments of a natural gas pipeline on Grauwyler Road between Tucasa Drive and Darr Street. Irving’s fire and police departments have been notified of the flaring. Learn more about the process.

  • MacArthur Boulevard - from Grauwyler Road to the eastbound Frontage Road of SH 183
    * Beginning Sept. 8
    : The northbound lanes of MacArthur Boulevard, from Grauwyler Road to the eastbound frontage road of SH 183, will be closed for the installation of water supply lines. Two-way traffic will be maintained within the existing southbound lanes of MacArthur Boulevard. Once utility work is complete, the northbound lanes will be repaved, and two-way traffic will be shifted to the northbound side so utility work can begin on the southbound side.

    The utility work will continue into April 2015 as part of Phase 1 of this project; the full scope of the project is anticipated to be completed by March 2016. There will always be two-way traffic on MacArthur Boulevard, one lane in each direction. View the traffic route map.

  • MacArthur Boulevard - Grauwyler Road to Rock Island (map)
    * Status:
    Expect lane closures in the right (outside) northbound and southbound lanes of MacArthur Boulevard between 7 a.m. and 4 p.m. for the installation of underground conduit through Oct. 31. In addition, expect periodic closures in the left (inside) lanes at the medians for the installation of street light bases and conduit. Two-way traffic will be maintained at all times. All lanes will be open after 4 p.m. Areas affected will be minimized to reduce traffic congestion while keeping the work zone safe for the construction workers.

  • Northgate Drive - Corridor Monuments at Carl Road and at Tom Braniff Drive (map)
    * Effective Tuesday, Sept. 2: Construction on new gateway wall monuments is under way along Northgate Drive at Carl Road and at Tom Braniff Drive. Expect lane closures on the westbound outside lane of Northgate Drive at the Carl Road intersection and on the northbound lane of Tom Braniff Drive at Northgate. Closures in both areas are anticipated through the end of November.

  • Royal Lane - Regent Boulevard to East 9th Street (map)
    Effective Monday, Aug. 11:  The northbound lane of Royal Lane will be closed intermittently between 8:30 a.m. and 4:30 p.m. daily from Regent Boulevard to East 9th Street for the delivery and placement of storm sewer pipes. This project is designed improve intersection drainage during the occurrence of heavy rain. The work is expected to be completed by mid-September.

  • Schulze Drive and Sowers Road - From Second Street to Larry Drive (map)
    * Status: Currently closed for the duration of the summer. The road closures will allow the contractor to transport building supplies and various equipment from the storage area without interruption. The closures are necessary to ensure the safety of residents. When school begins in the fall, it is anticipated the roadways will return to a partial closure status to allow for student access to local campuses.

  • Story Road - From Rutherford Street to Ridgewood Street (map)
    * Status: The southbound side of North Story Road from Rutherford Street to Ridgewood Street is closed for wastewater main construction. Two-way traffic will continue on the northbound side of Story Road, with a single lane in each direction. Residents whose driveways will be directly affected by the work will be provided access routes through the work zone. All businesses and residences will be accessible during construction. The contractor has begun installation of the sewer main under Story Road; more than 50 percent of the pipe has been installed at this time.

State/County/Regional Projects

Updated Aug. 29

From Northgate Drive to S.H. 183f