Built in 1964 and 1959 respectively, Lee and Lively Park swimming pools have not been operational since the 2019 aquatic season due to the COVID-19 mandated closures in 2020, staffing shortages and significant structural and operational damage caused by the winter weather freeze in 2021.
Assessment of Pools
In May 2022, an assessment was conducted on Lee and Lively Park swimming pools to examine all aspects of the pools and determine the existing issues, as well as necessary repairs and costs required to reopen the half-century-old pools to the public. Both pools have exceeded the average lifespan of an outdoor aquatic facility by 20 years.
The assessment found that repairing and updating the outdated pools would cost approximately $5-$6 million. Several issues were identified with each pool, including broken pipes and valves, regulatory/code compliance deficiencies, significant water loss due to cracks and deterioration, old cast iron piping, filtration and mechanical failures, safety concerns and more.