Irving's Road to the Future

Posted on: September 3, 2021

2021 Road to the Future Progress Report – Maintenance Operations Only

Members of City Council's Transportation and Natural Resources Committee heard an update on Sept. 2 from the Traffic and Transportation Department, Street Division, regarding the annual Summer Asphalt Overlay Program, as part of the Road to the Future program that started in 2017. Currently, Irving has approximately 798 centerline miles of roadway in the city. This is similar to a two-lane road from Irving to Nashville, Tennessee.  The results shown below illustrate the positive impact this program is accomplishing to address the roadway maintenance needs of the city.

City of Irving Road Maintenance Projects 2018-2021

  • 96 roads (56.8 centerline miles) have been improved, extending the pavement life at least 10 years.
  • 164 roads (33.4 centerline miles) received pavement restoration.
  • More than 800 pavement panels have been replaced.
  • 360 new crosswalks have been installed.
  • 87 traffic signals upgraded.

The short video below illustrates the progress made through Year 4 by overlaying each year's progress by color on a map of the city.

###

View more news and information about Irving’s infrastructure investments and Road to the Future projects.

Facebook Twitter Email

Other News in Irving's Road to the Future

A crew places fresh asphalt on Rock Island Road.

Summer Overlay Project Kicks Off

Posted on: May 6, 2022
Worker operates heavy machinery to dig up old pavement.

Infrastructure Explained

Posted on: April 4, 2017
Road to the Future - Irving TX

City Plans 'Road to the Future'

Posted on: November 11, 2016